It is our tentative prediction that a recent ruling from the Regional Administrative Court of Tuscany (TAR), which blocked the project to expand Florence Airport’s runaway – and hence, its passenger flow and corollary revenue – may “prepare the ground” for an investment arbitration dispute between Argentinian and Emirati investors and Italy.

 

Background

In 2009, the then Mayor of Florence, Matteo Renzi (future Italian PM), proposed the idea of building a runaway of 2,400 meters and a new terminal for the Florence Airport (“Amerigo Vespucci”) with the view of increasing its passenger flow. That idea met the support of the Region of Tuscany and the Argentinian tycoon, Mr. Eduardo Eurnekian, the majority shareholder of Corporación América Airports (CAAP), the world leading company in owning and operating airports. In 2014 CAAP acquired the majority ownership of Florence airport in order to present the “2014-2029 Masterplan” to expand the airport. The Masterplan is estimated to cost approximately € 334,500,000 and aims at doubling up passenger flow of the airport. Of this 334.5 million, the State committed to put 150 million, while the remainder 184.5 million would be put by the private investors managing the company that operates the airport.

The authorization process for the works started in 2015. On 28 December 2017, the Decree-Law containing a favorable Environmental Impact Assessment (EIA) for the project was issued by the Ministry of Environment (MoE). On 21 March 2018, seven municipalities adjacent to the city of Florence challenged the EIA Decree-Law before the TAR in order to block the project.

In the meantime, on 25 July 2018, CAAP sold 25% of its participation in Toscana Aeroporti S.p.A. (hereafter TA, the local company set up to run both Florence airport and Pisa airport) to Mataar Holdings 2 B.V., a company indirectly controlled by the Investment Corporation of Dubai (ICD), the sovereign wealth fund of the Emirate of Dubai.

On 6 February 2019, the decision-making body of the Conference of Services acknowledged that all the competent Administrations – including the Ministry for the Cultural Heritage – had given their favorable opinions for the Masterplan, despite the minority opposition of the seven municipalities. Accordingly, on 16 April 2019, the Minister of Infrastructure and Transport (MIT) ratified the outcome of the Conference of Services by issuing the Decree-Law that gave the green light to start the works.

However, the whole project has suffered a setback because on  27 May 2019 the TAR rendered its ruling n. 793/2019 upholding the challenge submitted by the seven municipalities, and thus annulled the EIA Decree-Law. The TAR found that the environmental assessment conducted by the MoE was not sufficiently exhaustive. Consequently, the MIT had to suspend its Decree-Law approving the Masterplan, while the Region of Tuscany, the municipality of Florence and TA have appealed the ruling to the Council of State (CS), the highest Administrative Court. The MIT’s Decree-Law will remain suspended until the resolution of the administrative dispute and so will the Masterplan for Florence airport. The CS is expected to rule on the matter in January 2020.

 

Reactions   

Bewildered by the TAR’s ruling that quashed the EIA Decree-Law, TA issued a press release criticizing its contents. To the company’s surprise, the administrative Judge:

“completely overturned the assessment given by the national ministerial commission of experts, supported and endorsed by the competent Ministers of three different national governments (Renzi, Gentiloni and Conte), regarding the suitability of the technical documentation to demonstrate the lack of negative impacts on the environment.”

According to the TAR, the Administration should have requested further details about the project before issuing the relevant EIA Decree-Law. The competent Administration instead concluded – wrongly, according to the TAR – that the assessment had been thorough and complete. However, Article 5 letter g of Legislative-Decree No. 152 of 2006 does allow the MoE to issue the EIA Decree-Law for a project having a level of details that are at least equivalent to that of the feasibility plan (as defined in the Legislative-Decree No. 50 of April 18, 2016), and in any event a sufficient level of details to permit a thorough assessment of the environmental impacts. And, indeed, the Department of Environmental Assessment of the MoE informed the Italian Civil Aviation Authority that it reached the following conclusion: “The planning documentation in the procedure’s archives may be regarded as adequate for the purposes of Environmental Impact Assessment rules.”

Moreover, the company has emphasized that it was not TA that came to the conclusion that the details of the project were sufficiently adequate for obtaining a favorable EIA; it was the competent technical departments of the Ministry that came to that conclusion. TA has affirmed that it did everything it was asked to in the course of the administrative procedure. Further, the company complained about the arbitrariness of the judgement, which does not address legal points; rather, it assesses technical matters of the project. Apparently, the TAR — without any court-appointed expert — discarded a complex two-and-a-half-year study conducted by qualified ministerial technical experts on the same day as the hearing, which is when the judgement was rendered. In that judgment, the TAR also suggests that that the ministerial Environmental Observatory (tasked with verifying compliance with the requirements) should have been more inclusive towards the municipalities opposed to the project, even if the Observatory was not mandated by the law to do so.

 

Potential Arbitrations

TA’s largest shareholders are indirectly Argentinean and Emirati investors. To be precise, CAAP is incorporated in Luxemburg, however, its main shareholder is the Argentinean mogul, Mr. Eurnekian; while Mataar Holdings 2 B.V is a Dutch registered company controlled by the Emirati ICD.

Both Argentina and the United Arabs Emirates have a BIT in force with the Italy. Both shareholders meet the definition of qualified investors under the legal instruments in question: Mr. Eurnekian as an Argentinean citizen pursuant to Article 1(2)(a) of the Argentina-Italy BIT, whereas the UAE-Italy BIT specifically protects also State-owned entities, such the sovereign wealth fund of Dubai at Article 1(2).

Mr. Eurnekian’s and ICD’s indirectly owned shares in TA meet the definition of a qualified investment as per Article 1(b) of both BITs. Accordingly, both foreign shareholders could avail themselves of the protection under the corresponding BITs made effective through the investor-State arbitration contemplated in both Treaties.

Article 2 of both BITs provides for a fair and equitable treatment (FET) that shall be accorded to the foreign investors of the other Contracting Party.

Admittedly, TAR’s ruling has frustrated Mr. Eurnekian’s and ICD’s’ legitimate expectations of doubling up the passenger flow and, accordingly, the revenue of their asset. Arguably, those frustrated legitimate expectations have been built up on various approvals by the local and central Administration. Three different ministers over a period of three years and three successive governments have endorsed investors’ project to increase the airport’s capacity. Consequently, the Italian State has fully backed-up investors’ legitimate expectations with respect to their qualified investment.

Finally, either the TAR arbitrarily came to the wrong conclusion (because the Administration had sufficient details about the project to issue the EIA) or the TAR was correct (because the Administration negligently did not request further details about the project before issuing the EIA). In either scenario, the Italian State first encouraged and then let down investors’ legitimate expectations by failing to ensure a favorable, stable and predictable legal framework for the investment at hand. Therefore, Italy could be held liable for breaching its FET obligation before the arbitral tribunals constituted under the Italy-Argentina/UAE BITs.

Additionally, an umbrella clause claim could be available by combining the Most-favored Nation (MFN) clause of the Italy-Argentina/UAE BITs with the Italy-Panama BIT. Arguably, Italy breached also that clause by rolling back the fair value over the construction services that would have been provided by the private investors in TA corresponding to the adequate margin over 184.5 million euros worth of construction services.

From investors’ perspective, a double investment arbitration would be more appealing than just appealing to the CS in terms of claimable damages. A favorable decision to the investors by the CS is not going to compensate the loss of profits that has already materialized due to the postponement of the works. Legitimate interests do not receive the same level of protection under national law as they do under investment law. In this sense, an international arbitration is more attractive as the applicable law to the dispute takes into account such future loss of profits. Therefore, an hypothetical award quantifying the damages may realistically range from several dozen million euros (in case the Masterplan is simply delayed) to several hundred million euros (in case the execution of the Masterplan is rejected once and for all by the CS).


________________________

To make sure you do not miss out on regular updates from the Kluwer Arbitration Blog, please subscribe here. To submit a proposal for a blog post, please consult our Editorial Guidelines.


Profile Navigator and Relationship Indicator
Access 17,000+ data-driven profiles of arbitrators, expert witnesses, and counsels, derived from Kluwer Arbitration's comprehensive collection of international cases and awards and appointment data of leading arbitral institutions, to uncover potential conflicts of interest.

Learn how Kluwer Arbitration can support you.

Kluwer Arbitration
This page as PDF

2 comments

  1. Danilo, Josep,
    As a long-time resident of both Florence and Sesto Fiorentino (one of the opposing adjacent towns), I feel compelled to note the unique opportunity presented by the Florence International Mediation Chamber, http://www.fimcmediation.com/ and the area’s strong embrace of mediation, including in the local legal community, the university, and the commercial courts (which are separate from the TAR).
    As the second institution in the world after Singapore focused entirely on international mediation, the FIMC has relied on guidance provided by the International Mediation Institute (IMI), which includes its task force to establish competency standards for investment mediation. See https://www.imimediation.org/about/who-are-imi/ism-tf/ In the absence of party agreement, the FIMC will appoint mediators holding an IMI certification of quality.
    Further, the FIMC has cooperation agreements with the Permanent Court of Arbitration (PCA) for the use of its modern arbitration and mediation facilities, which overlook the Arno, just behind the famous Uffizi gallery. The parties could not find a better place to attempt to resolve their dispute. http://www.fimcmediation.com/cooperation-agreements/
    Finally, you will not find a prime minister more enthusiastic about the possibilities offered by mediation than Italy’s Giuseppe Conte. In fact, on this blog I once wrote about an experience with Prof. Conte as an arbitrator who recommended that we (the parties) attempt mediation to settle our dispute (he was the chair of the tribunal mentioned in the post): https://arbitrationblog.kluwerarbitration.com/2011/09/13/anti-arbitration-its-not-hard-to-mediate-during-arbitral-proceedings/?print=pdf
    With this robust framework in place for mediation, it would seem a genuine pity not to take advantage of it.
    Michael Mcilwrath

    1. Dear Michael,

      Thank you very much for taking the time to read our post and, especially, thank you so much for your extremely interesting comment.

      An Investment Mediation is indeed another option that is worthy to be considered carefully. In particular, the dispute at hand lends itself to reach a settlement or at least to attempt to reach one. For instance, in case the Masterplan cannot be executed, the State may agree:

      – firstly, to extend the concession period – free of charge – by a number of years that would make up for the loss of profits that the airport would have earned instead thanks to the Masterplan (please note that the concession period is due to end in 2043);
      – secondly, to compensate proportionally Toscana Aeroporti Spa – during the term of the extended concession – for the further loss of passenger flow every time an improvement of the facilities of a competing airport (such Bologna or Roma Airports), and/or an improvement of a competing airport’s rail/road connections with Florence area, and/or an increase of the routes served by a competing airport is authorized by the competent bodies (as you may know Florence Airport’s traffic is often taken by Bologna or Roma Airports as they have a longer runaway, serving more destinations, and where bigger aircrafts can land carrying more passengers, some of which have to land at Rome or Bologna even if they are heading to Florence).

      Of course, given its stellar reputation, the Florence International Mediation Chamber may be the perfect Institution to administer a possible mediation, which may be inserted in the six-month cooling-off period between the notice of dispute and the request for arbitration under the UAE-Italy BIT, along the same lines of your post titled “Anti-Arbitration: It’s Not Hard to Mediate During Arbitral Proceedings” which I read with great interest.

      Kind regards,
      Danilo

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.